From Grant Award to Financial Close: Why Innovation Fund Projects Face Implementation Risks

Share:

Innovation Fund Insights · Article 3 of 5

By Yasir Khan · Published 9 November 2026

Why financing, permitting, infrastructure and market readiness can determine whether an innovative project moves into operation.

Winning an Innovation Fund grant is an important milestone for a company developing an innovative low-carbon technology. It can validate a project’s potential, support its financing strategy and help attract additional investors. Yet a grant award does not guarantee that the project will be built.

Industrial decarbonisation projects often require substantial capital investment, long development schedules, new infrastructure, complex permitting and reliable commercial arrangements. Even after a project has been positively evaluated, changes in financing conditions, construction costs or market demand can threaten its viability.

The European Commission’s 2026 evaluation found that about 40% of projects reported delays before financial close. Among projects that had reached financial close, about 63% experienced delays before entry into operation. By the end of Q1 2025, 16 of 208 projects with signed grant agreements had been terminated prematurely. These figures describe different stages of implementation: a delay is not the same as a cancellation.

The central questionThe evidence raises a practical policy question: are financing structures and implementation requirements sufficiently aligned with the commercial, regulatory and infrastructure risks faced by first-of-a-kind industrial projects? The sources do not establish that grant design alone causes failure; they show that delivery is exposed to risks that can evolve after evaluation.

Innovation Fund implementation snapshot comparing Commission project-delay and termination data at Q1 2025 with ECA cancellation/withdrawal data at 30 June 2025; denominators and periods are explicitly distinguished.
Figure 1. Different indicators, different reporting cut-offs. Commission: SWD(2026) 199 final; European Court of Auditors: Special Report 11/2026.

What is financial close, and why does it matter?

Financial close is the point in project implementation when financing and contractual arrangements are sufficiently secured for the project to move from planning into construction. For an Innovation Fund project, it is a key milestone because the funding award must be translated into a bankable, deliverable investment.

Depending on the project, reaching financial close may require committed equity and debt, lender approvals and conditions precedent, major procurement and construction arrangements, permits, offtake agreements and credible plans for any essential external infrastructure. The exact conditions vary by project, funding route and grant agreement.

The Innovation Fund framework includes a maximum four-year horizon for reaching financial close. The applicable grant agreement sets the project’s milestone and timetable. The European Court of Auditors notes that the Commission cannot extend financial close beyond the four-year limit set in legislation, even where it considers a project’s size or degree of innovation relevant to timing.

Financial close is therefore not a procedural formality. It is the point at which a project’s technology, financing plan, commercial case and implementation conditions must align sufficiently to permit construction to proceed.

1. Financing gaps: a grant does not fund the entire project

The most important factor behind delays is often the ability to secure the remaining capital. Large industrial projects can have high capital expenditure, long construction periods and uncertain early revenues. The grant may improve the project’s risk-return profile, but does not remove the need to finance the balance or cover costs that fall outside the grant’s relevant-cost calculation.

Under regular Innovation Fund calls, support can cover up to 60% of relevant costs, subject to the call methodology and conditions. Relevant costs are not necessarily the same as the project’s full capital expenditure. Developers must therefore assess the complete funding requirement, including co-financing, costs outside the eligible base and liquidity needs during development and construction.

The Commission’s evaluation identifies difficulty raising capital, substantial cost increases and changing market conditions among the recurring reasons why projects withdraw during grant agreement preparation or later struggle to proceed. Financing gaps may widen if costs rise, revenues are delayed or potential investors reassess the risk.

What project developers can do

  • Prepare a complete sources-and-uses model that distinguishes the grant, equity, debt, national support and other sources, and clearly identifies any remaining gap.
  • Stress-test the financial model against cost escalation, longer construction, weaker offtake prices, delayed revenues and financing costs.
  • Keep the financing timetable aligned with permitting, procurement and construction milestones; avoid relying on an uncommitted source of capital to close the case.

Practical implicationA funding plan is strongest when it explains not only how the project is expected to be financed, but also how the project team will respond if one of its principal assumptions changes.

2. Offtake agreements and market demand: the commercial case must hold

Projects producing low-carbon materials, renewable hydrogen, synthetic fuels or other innovative products may depend on buyers accepting a price premium, committing to long-term purchases or meeting specific technical and sustainability requirements. In emerging markets, demand and pricing can be difficult to forecast.

The Commission and CINEA identify securing offtake as a recurring challenge. If a buyer delays or cancels an agreement, the project may lose an important source of expected revenue. That can weaken debt capacity, alter the business case and create a financing gap even when the technology remains promising.

What project developers can do

  • Distinguish signed contracts from term sheets, memoranda of understanding and expressions of interest.
  • Check whether demand, pricing and volume assumptions are supported by credible market evidence.
  • Where feasible, diversify buyers or identify back-up offtakers and examine how lower volumes or prices would affect cash flow.

3. Permitting: a schedule risk with financial consequences

Permitting can affect the entire critical path. Industrial projects may need environmental approvals, construction permits, operating authorisations and other regulatory decisions. Requirements can vary between jurisdictions, and innovative technologies may not fit neatly into existing procedures.

CINEA’s 2025 Annual Knowledge Sharing Report presents evidence from a targeted permitting survey that received 90 replies. In that survey, 68% of projects identified permitting among their top challenges, more than 10% identified it as their primary challenge, and about half reported a concrete risk of delay linked to permits or permitting procedures.

The report also records an average of 16.1 months from the start of permit preparation to submission, and a further average of 16.4 months from submission to the granting of permits. These are survey results from the responding project coordinators, not universal statutory timelines or a forecast for every project.

What project developers can do

  • Prepare a permit register identifying each approval, responsible authority, dependencies, expected duration and status.
  • Identify which permits are critical to financial close, construction and operation, and build realistic float into the schedule.
  • Engage early with permitting authorities and project partners; investigate whether procedures can lawfully run in parallel.

4. External infrastructure: dependencies beyond the project boundary

A decarbonisation project may rely on infrastructure that the project company does not control. Examples include grid connections, hydrogen pipelines, electricity transmission capacity, CO₂ transport and storage, water supply and shared industrial utilities. If a necessary connection or network is delayed, a technically complete facility may not be able to operate as planned.

The Commission’s evaluation and CINEA’s knowledge-sharing work both identify external infrastructure as a recurring implementation risk. This is particularly important where a project forms part of a wider industrial cluster or depends on a transport and storage network that is still being developed.

What project developers can do

  • Map every critical third-party dependency and record its maturity, owner, contractual status and planned delivery date.
  • Where possible, move from non-binding statements of intent to agreements with clearly defined responsibilities, milestones and escalation routes.
  • Assess fallback options and schedule implications if a connection or shared facility becomes available later than expected.

5. Cost escalation and supply chains: keeping the business case viable

Higher equipment prices, construction inflation, supplier shortages and longer lead times can widen the funding gap and postpone commissioning. The risk is especially relevant for first-of-a-kind installations that depend on bespoke equipment or a limited supplier base.

CINEA’s 2025 knowledge-sharing report describes projects using financial contingency buffers, renegotiating agreements, securing additional financing, diversifying suppliers, revising delivery schedules and exploring local sourcing to manage cost and supply-chain shocks.

What project developers can do

  • Use a transparent cost-estimate basis and document which elements are budget quotes, firm offers or preliminary assumptions.
  • Identify long-lead items, single-source components and the procurement decisions that affect the critical path.
  • Set and justify contingency levels, including the approval process for drawing on contingencies or seeking additional finance.

6. Project governance and technical validation still matter

Not every implementation problem originates outside the project. Changes in key partners, unclear responsibilities, technical redesign, additional testing or weak decision-making can also affect the schedule and financing plan. The Commission’s evaluation notes that project difficulties frequently arise from several interacting factors rather than a single cause.

A consortium may have excellent technical expertise yet lack a clear owner for procurement, permits, financial close or commercial agreements. In such cases, decisions can be delayed and one workstream can progress without the others being ready.

What project developers can do

  • Assign accountable owners for finance, engineering, procurement, permitting, offtake and grant obligations.
  • Establish a change-control process that assesses the effects of redesign or partner changes on costs, milestones, permits and grant conditions.
  • Build testing and validation activities into the project schedule, including the evidence needed to move from one stage to the next.

The implementation gap in numbers

The Commission’s and the ECA’s findings need to be read together, but they do not measure exactly the same cohort. At the end of Q1 2025, the Commission reported 16 premature terminations among 208 projects with signed grant agreements. The ECA later examined the cohort selected for support by 30 June 2025: of 228 selected projects, 20 were withdrawn before grant agreement signature and 20 were terminated after signature. The ECA’s 40-of-228 figure is therefore a cancellation-or-withdrawal rate among initially selected projects, not a termination rate among signed grants.

The ECA also reported that, by 30 June 2025, €12.3 billion was available for projects: €11.6 billion had been assigned through grant agreements and €0.7 billion had not yet been allocated. Payments to projects amounted to €331.8 million, or 2.7% of the €12.3 billion available-for-projects amount and less than 1% of the Fund’s expected €40 billion budget.

ECA snapshot at 30 June 2025: €12.3bn available for projects, comprising €11.6bn assigned and €0.7bn not yet allocated; €331.8m paid, or 2.7%. Milestone-payment caveat included.
Figure 2. ECA financial snapshot at 30 June 2025. The €12.3bn amount includes €0.7bn not yet allocated; payments are milestone-based. Source: ECA Special Report 11/2026, paragraph 36.

This disbursement figure requires context. Innovation Fund payments are linked to milestones: up to 40% of the grant may be disbursed at financial close or at an agreed earlier milestone, with further amounts paid after financial close and potentially in annual instalments after entry into operation. The low cash-paid share therefore reflects the milestone model and the fact that many projects had not yet reached the relevant milestones. The ECA nevertheless concluded that project delays and terminations were contributing to slow deployment of funds.

Do not conflate the measuresGrant award, grant agreement signature, financial close, cash disbursement, entry into operation and project cancellation are distinct events. Use the relevant denominator, reporting date and definition whenever quoting a percentage.

Five practices that support delivery

The official findings do not establish a single formula for success. They do, however, support a practical set of steps for reducing avoidable delivery risk.

  • Stress-test the financing model and identify the point at which a gap becomes unbridgeable.
  • Secure credible offtake arrangements early and avoid relying on a single commercial assumption where practical alternatives exist.
  • Start permitting work early, track the critical path and maintain active engagement with relevant authorities.
  • Confirm infrastructure dependencies with named counterparties, milestones and escalation routes.
  • Build delivery-ready governance that aligns engineering, procurement, finance, commercial arrangements and grant obligations.
Five delivery practices: stress-test finance, secure offtake, start permitting early, confirm infrastructure dependencies and build delivery-ready governance.
Figure 3. Practical risk-management practices synthesised from the Commission evaluation and CINEA knowledge-sharing findings.

What happens when a project is delayed?

A delay does not automatically mean that a project will be cancelled. Schedules may be amended and problems can sometimes be resolved through additional financing, revised procurement or changes to implementation plans, subject to the applicable grant agreement and approval process.

The important distinction is between a manageable deviation and a fundamental change that undermines the project’s viability or its grant conditions. The Commission’s evaluation notes that monitoring and ongoing exchanges can help identify problems early, while the ECA highlights cases where projects were cancelled after their financing could not be secured, costs changed materially or key partners departed.

Project teams should therefore monitor critical milestones throughout delivery and communicate material changes early to the relevant financiers, partners and programme authorities. Waiting until a deadline is close can reduce the options available to resolve the issue.

How Impact Funding Europe can help

For capital-intensive projects, funding strategy and implementation planning should be developed together. The technical case, financing structure, market assumptions, permitting strategy and delivery schedule need to support a coherent plan.

Impact Funding Europe supports companies preparing applications for European funding programmes. Depending on the project and agreed scope, relevant support may include funding strategy, application preparation, review of project maturity, assessment of financing assumptions and structured consideration of implementation risks.

You can also explore the Innovation Fund calls and auctions or review all EU funding opportunities.

Planning an Innovation Fund application for an industrial project? Contact Impact Funding Europe to discuss the funding route and the main technical, financial and delivery issues to address before submission.

Planning an Innovation Fund application for an industrial project?

Sources and reporting notes

Official sources

  • European Commission – Evaluation of the Innovation Fund’s operation, SWD(2026) 199 final (July 2026). Open source
  • European Court of Auditors – Special Report 11/2026, Innovation Fund – High potential, but slow progress and little impact on emissions reduction (published 20 March 2026). Open source
  • CINEA – 2025 Annual Knowledge Sharing Report of the Innovation Fund, including the permitting survey findings. Open source
  • EU legislation – Commission Delegated Regulation (EU) 2019/856, including project maturity and milestone-based grant disbursement rules; check the consolidated version applicable to the call. Open source

This article is general information. It does not replace the applicable call documentation, grant agreement, financial agreements or project-specific legal advice.

↑ Back to top


Innovation Fund Insights · Article 1 of 5

By Yasir Khan · Published 26 October 2026

A practical guide for companies developing innovative low-carbon projects in Europe

The EU Innovation Fund supports the demonstration and deployment of innovative low-carbon technologies that can help decarbonise European industry. But a promising technology alone is not enough to secure support. Applicants need to demonstrate meaningful innovation, credible emissions reductions, convincing project maturity and a realistic pathway to implementation.

The European Commission’s 2026 evaluation of the Fund’s operation offers an evidence-based view of how the programme has performed and where applicants continue to face challenges. Its portfolio data largely cover the period up to the first quarter of 2025, so the figures below should be read as a snapshot of the Fund’s early implementation – not as a statement of current call status.

Programme fundingThe Innovation Fund is financed by EU ETS allowance revenues; the ECA describes an estimated envelope of around €40 billion for 2020–2030.
Portfolio at end March 2025208 projects had been awarded grants; 192 remained ongoing, with €11.6 billion in committed support.
Expected climate impactThe 192 ongoing projects were expected to avoid 871 million tonnes of CO₂-equivalent emissions over their first decade of operation.
Investment mobilisationThe Commission’s analysis reported €45.2 billion in expected/planned total investment against €11.08 billion in grants; planned CAPEX was used as a proxy.

Source reports: European Commission evaluation (SWD(2026) 199 final) | European Court of Auditors Special Report 11/2026

For organisations preparing an Innovation Fund application, the report points to seven practical lessons.

Of 1,589 submitted proposals, 1,342 were eligible and 517 passed all evaluation thresholds.
Commission evaluation data on submitted, eligible and above-threshold proposals; evaluation data through Q1 2025. Passing thresholds does not guarantee funding.

1. Demonstrate genuine innovation – and explain the role of public support

The Innovation Fund is not a general decarbonisation grant. It is designed to support innovative technologies, processes, products and solutions with significant potential to reduce greenhouse gas emissions. The evaluation identifies the degree of innovation as a core element of the regular-grant assessment and notes that projects similar to previously funded solutions must explain what is new about their own proposal.

Applicants should establish a clear baseline against which their technology can be assessed. Explain what is technically or commercially new, how the proposed solution differs from the current state of the art, and why the innovation matters for the relevant industrial process or market.

The funding rationale should also be credible. Although “additionality” should not be presented as a standalone award criterion unless the applicable call says so, the project narrative and financial plan should clearly explain the funding need, the investment barriers and the role Innovation Fund support is expected to play in enabling or accelerating deployment.

Where comparable technologies have already received support, avoid relying on broad claims such as “first of its kind” or “revolutionary” without evidence. Identify the specific differentiators – such as scale, application, performance, process integration or deployment conditions – and substantiate them.

IFE insight

A clear innovation case moves beyond describing the technology. It explains what changes compared with existing solutions, why that change matters and how the project supports credible industrial decarbonisation.

2. Match project maturity to the right call

The Commission evaluates project maturity across technical, financial and operational dimensions. Technical maturity concerns the feasibility of the expected outputs, knowledge of technical risks and proposed mitigation measures. Financial maturity concerns the credibility of the business model and financing plan, including the ability to reach financial close within the applicable timeframe. Operational maturity looks at the implementation plan, the project team and the status of permits, licences and regulatory procedures.

These dimensions must reinforce one another. A technically promising project can still appear unready if critical permits are missing, the delivery schedule is unrealistic or the financing plan relies on unsupported assumptions. Applicants should assemble evidence proportionate to the project and the chosen call, including engineering studies, risk registers, implementation schedules, financing plans and a realistic account of outstanding approvals.

Call choice matters, too. Project size, technology area, readiness and the specific topic all affect which call or funding route is appropriate. Do not assume that a project eligible for one Innovation Fund call will automatically fit another. Review the current call fiche and its definitions, eligibility rules, award criteria, cost methodology and submission requirements before building the application around them.

The Commission also found that tailored Project Development Assistance (PDA) has helped some initially unsuccessful proposals address maturity gaps. By 2024, 16 of the 37 PDA beneficiaries who reapplied had secured an Innovation Fund grant – a 43% success rate among those reapplicants. This is not a general success-rate forecast: PDA recipients were selected from among promising proposals, and the Commission cautions against treating the result as a causal comparison.

Practical check

Can the project team show where the project stands today, what remains to be completed, who owns each action and how the remaining work fits the grant and financial-close timetable?

3. Build a greenhouse gas calculation that stands up to scrutiny

Greenhouse gas (GHG) emissions avoidance is central to the Innovation Fund. A weak calculation can undermine the credibility of an otherwise promising project. The Commission’s evaluation highlights three aspects of the assessment: absolute emissions avoidance, relative emissions avoidance and the quality of the calculation.

Applicants should identify and justify the reference scenario, define the relevant system boundaries and use traceable, defensible data. Assumptions about production volumes, energy consumption, feedstock use, emissions intensity and operating performance should be aligned with the technical design and financial model, where relevant. Any material uncertainty should be treated transparently rather than hidden inside optimistic assumptions.

A large headline figure for tonnes of CO₂ avoided is not sufficient by itself. Evaluators need to understand how the result was calculated and why the baseline is appropriate. GHG calculations should therefore be developed in parallel with the technical and financial case – not treated as a formality to finish at the end of the application.

The legal framework also links part of the grant support paid after financial close to verified emissions avoidance during the reporting period. Under Article 8 of Delegated Regulation (EU) 2019/856, where total verified emissions avoidance over that period is below 75% of the planned total, the relevant amount paid or payable after financial close is proportionally reduced or recovered, subject to the regulation’s provisions and exceptions. Exact obligations should be checked against the regulation and the project’s grant agreement.

IFE insight

An emissions calculation should be traceable from source data to final result. Align the reference scenario, technical assumptions and financial model, and verify all call-specific methodological requirements before submission.

Seven lessons: innovation, project maturity, GHG avoidance, cost efficiency, financial close, delivery-ready team and replicability.
Figure 2. Seven practical lessons for preparing an Innovation Fund application.

4. Demonstrate cost efficiency and value for money

The regular-grant assessment considers cost efficiency in relation to the grant requested and the project’s absolute GHG emissions avoidance. Applicants should make sure that the requested support, eligible or relevant costs, emissions calculations and financial assumptions are consistent with the methodology set out in the call.

A strong financial case needs more than a large project budget or a high emissions-reduction claim. It should use credible cost estimates, clearly explain the assumptions and show how the requested support relates to the project’s expected climate benefits. Errors or incomplete calculations can weaken an application even when the technology is attractive.

For most topics, the Commission’s evaluation says cost-efficiency ratios above €200 per tonne of CO₂-equivalent lead to rejection, but thresholds differ for some topics, including pilots. Treat this as call-specific: check the relevant call fiche and scoring formula, especially where future call terms have not yet been published.

Similarly, regular Innovation Fund grants can cover up to 60% of relevant costs under the applicable methodology and conditions. This is not a promise to cover 60% of every project’s total capital expenditure. Applicants need a clear view of which costs are relevant and eligible, what the grant can cover and how the remaining investment will be financed.

The Commission’s investment-mobilisation analysis reported around €45.2 billion in total expected or planned investment against €11.08 billion in grants, a ratio of roughly four to one. This was based on applicant-reported planned capital expenditure as a proxy. It should not be represented as a final audited measure of investment realised by all projects.

Comparison of €45.2 billion in expected or planned investment with €11.08 billion in grants.
The Commission reported €45.2 billion in expected/planned total investment against €11.08 billion in grants in its investment-mobilisation analysis; applicant-reported planned CAPEX is used as a proxy.

Preparing an Innovation Fund application and want a second pair of eyes?

5. Plan for financial close from day one

Winning a grant is not the same as delivering a project. The Commission’s evaluation identifies financing gaps and changing market conditions among the principal causes of project delays and withdrawals. Difficulties raising capital, cost increases and an inability to secure offtake agreements can all affect project viability.

Applicants should develop a financing strategy that goes beyond the amount requested from the Innovation Fund. It should explain the total investment required, the expected grant contribution, other sources of finance, the status of financing discussions and the assumptions that underpin projected revenues and operating costs. Any material dependencies should be identified clearly.

Financial close also depends on delivery readiness. The project plan should identify the permits, licences, construction arrangements, partner commitments and commercial agreements that remain outstanding, together with realistic timelines and mitigation measures. For projects that rely on future infrastructure – such as grid connections, hydrogen pipelines or CO₂ transport and storage – explain the dependency and the status of the relevant arrangements.

The European Court of Auditors’ 2026 audit provides a separate warning about implementation risk. It found that, by 30 June 2025, 40 of 228 projects initially selected for support had been cancelled or withdrawn: 20 before grant agreements were signed and 20 after signature. This is a different measure from the Commission evaluation’s count of terminated signed projects. It nevertheless reinforces the importance of realistic maturity assessments and financing plans.

Practical check

For every major financing, permitting, infrastructure or offtake dependency, record its current status, the accountable party, the expected completion date and the consequence if it is delayed.

6. Show that the delivery team and value chain can execute the project

Project maturity is not only a matter of technology and spreadsheets. It also depends on whether the organisation or partnership responsible for delivery has the capabilities, governance and commitments needed to bring the project into operation.

Where a project relies on multiple partners, the application should make the division of responsibilities clear. Technical providers, industrial hosts, engineering and construction partners, feedstock or energy suppliers, offtakers, infrastructure operators and financing partners may all be important, depending on the project. Their roles should be credible and reflected in the implementation schedule and risk plan.

A consortium is not a formal requirement for every Innovation Fund project. The principle is to demonstrate that the proposed delivery structure is appropriate to the project’s complexity and that essential capabilities are covered. Unclear responsibilities, dependence on a single key partner or assumptions about unconfirmed commercial relationships can create avoidable weaknesses.

The project should also explain how it fits into the wider value chain. For industrial decarbonisation, this may include access to reliable low-carbon energy, transport and storage infrastructure, sustainable inputs, customers for the resulting product and the relevant permitting framework. These elements help connect the proposal’s technical ambition to its real-world implementation conditions.

7. Explain how the project can be replicated and scaled

The Innovation Fund is designed to support projects with the potential to contribute to broader decarbonisation, not just deliver a single successful installation. Replicability is therefore a core part of the regular-grant assessment.

A strong proposal should explain where and how the technology could be deployed beyond the first site, what future efficiency or environmental gains may be possible, and which conditions would enable replication. Depending on the project, these might include standardised equipment, lessons from demonstration, cost reductions, compatible infrastructure, transferable operating practices or the development of a stronger European supply chain.

The case should remain realistic. Distinguish what the initial project will demonstrate from what might be achieved at additional sites or at larger scale. Set out assumptions, prerequisites and potential barriers. Avoid unsupported claims about the number of future installations, market share or emissions savings that the project itself will not directly deliver.

The Commission’s evaluation reports that the 192 ongoing projects were expected to avoid 871 million tonnes of CO₂-equivalent emissions over their first decade of operation. This is a portfolio-level projection, not a realised emissions outcome, and it does not automatically measure the wider replication impact of each project. The role of an applicant is to present a credible project-specific case for how its innovation can support wider deployment.

What these lessons mean for prospective applicants

The Commission’s evaluation shows that a competitive Innovation Fund application requires consistency across the technical, environmental, financial and operational case. The technology must be genuinely innovative, the emissions calculation must be defensible, the cost-efficiency case must follow the applicable methodology, and the financing and implementation plan must stand up to scrutiny.

The evaluation’s proposal data also underline the competitive nature of the programme. Across the proposals covered by its summary, 1,589 were submitted, 1,342 were eligible and 517 passed all evaluation thresholds. Passing thresholds does not necessarily guarantee funding: proposals also compete within the available budget, and high-quality proposals can remain unfunded when demand exceeds resources.

A practical preparation process should therefore begin well before submission. Confirm the right call, test the project’s maturity, align the technical and financial models, verify the GHG methodology and identify the evidence needed to support every significant claim. The current call documentation remains the controlling source for eligibility, scoring and submission requirements.

Looking ahead: IF26 calls (time-sensitive)

As of 15 October 2026, the European Commission’s calls page states that five IF26 calls are planned to open in December 2026: Net-Zero Technologies, SME, Maritime, Heat Auction and Hydrogen Auction. The planned SME call has a €200 million budget and is intended for SME projects with €2.5 million–€20 million in capital expenditure, with two application rounds indicated. Dates and conditions are indicative until confirmed in the published call documents. Check the live Commission pages before relying on these details.

How Impact Funding Europe can support your Innovation Fund application

Preparing an Innovation Fund application requires technical, environmental, financial and commercial information to support one coherent case for funding. Impact Funding Europe provides EU grant-writing and funding support for organisations developing smart, digital and climate-neutral projects, including proposal writing, consortium building, fund matching and project administration.

For a prospective applicant, an early discussion can help identify the relevant funding route, clarify the work needed to prepare a competitive proposal and surface gaps in the project’s technical, financial or operational case.

Considering an Innovation Fund application?

Contact Impact Funding Europe to discuss your project and the appropriate next steps.

This article reflects the European Commission’s 2026 evaluation of the Innovation Fund’s operation and portfolio data up to the first quarter of 2025. Figures are a snapshot of the Fund’s early implementation and not a statement of current call status. Call dates and conditions are indicative until confirmed in the published call documents; check the live Commission pages before relying on these details.

↑ Back to top


Leaf l green.png

Clean Energy

In 2019 the EU completed a comprehensive update of its energy policy framework to facilitate the transition away from fossil fuels towards cleaner energy and to deliver on the EU’s Paris Agreement commitments for reducing greenhouse gas emissions.

The agreement on this new energy rulebook – called the Clean energy for all Europeans package – marked a significant step towards the implementation of the energy union strategy, published in 2015.

Climate, Energy and Mobility is the focus for Cluster 5 in Horizon Europe. This clusters aims to fight climate change by better understanding its causes, evolution, risks, impacts and opportunities, and by making the energy and transport sectors more climate and environment-friendly, more efficient and competitive, smarter, safer and more resilient

More information here.

Recent Projects

Mortiz Thiede

Dr. Mortiz Thiede

Financial Modelling & Loan Facilities

Dr. Moritz Thiede strengthens Impact Funding Europe’s finance work with robust modelling and debt-structuring expertise. Trained as an economist (Diplom-Volkswirt), he has served as a Senior Consultant delivering complex company analyses, controlling systems, restructuring support, and financing advisory.

He builds bankable financial models, develops scenarios that survive stress tests, and translates project narratives into lender-ready numbers—cashflow logic, covenants, and repayment capacity. Moritz supports clients in structuring loan facilities, negotiating term sheets, and aligning funding strategy with operational reality, including blended finance approaches where grants and debt must fit together cleanly. He works comfortably with lenders and investors alike.

Olaf Gerd Gemein

Olaf Gerd Gemein

Verocity

Olaf is a passionate Serial Entrepreneur and Business Architect with a specific ambition: to be a change catalyst!

With over 30 years of practical experience in various markets in Europe, Asia, North and South America and Canada, he has successfully supported more than 100 projects in the ICT sector. His contributions have focused on accelerating start-up and innovation clusters, building networks, products and services from scratch, facilitating and implementing go-to-market strategies. He is frequently asked to speak at conferences and facilitate networking on smart tech topics around the world.

Peter Schottes

Peter Schottes

Eisenschmidt Consulting

Peter holds a PhD in nature science (climate impact research), worked as a project manager for software development and as a freelance consultant. He is managing director and shareholder of Eisenschmidt Consulting Crew in Kiel, Germany. He is a specialist in transformation projects and works as a sparring partner for top executives. His focus in on strategy development, digital transformation and concept development.

Peter is active as advisor for StartUps and Angel investor. At IFE he overlooks the entire process of community building, stakeholder management and is also responsible for the project kick-offs.

Alex neu

Alex Chalkley

Venturenomix

Alex has a BSc in Mathematics, Economics & Computing and has already built a market-leading R&D Funding Consultancy in the UK from 2009 to 2019. Alex has developed funding bids, mainly in the form of R&D Grant Applications, that have secured over €60m for clients operating at the forefront of technology innovation. Venturenomix, focuses on supporting Impact Ventures by offering specialist funding related consultancy services to ambitious people seeking funding for good projects. At IFE, Alex is Managing Director and responsible for all aspects of the business, in particular recruiting, mentoring and adding value to the EU Grant Writing Consultants working on multi-million Euro EU Grant Applications.

Smart city l green

Smart City

A smart city is a place where traditional networks and services are made more efficient with the use of digital and telecommunication technologies for the benefit of its inhabitants and business. 

A smart city goes beyond the use of information and communication technologies (ICT) for better resource use and less emissions. It means smarter urban transport networks, upgraded water supply and waste disposal facilities and more efficient ways to light and heat buildings. It also means a more interactive and responsive city administration, safer public spaces and meeting the needs of an ageing population. Last not least, it aims to make a city a healthier, more sustainable and more attractive place to be for its residents and visitors.

More than half of the world’s population now lives in urban areas. This is expected to reach 80% by 2050. Cities and metropolitan areas are centres of economic activity, knowledge generation, innovation and new technologies. Cities influence the quality of life of citizens who live or work in them and they are major contributors to global challenges.

A mission in this area will help us meet the goals and targets set out by international policy frameworks such as the COP21 Paris Agreement, the UN’s Sustainable Development Goals (notably SDG11), the Urban Agenda for the EU and the Habitat III New Urban Agenda as cities play a key role in all of them.

Read more here.

Recent Projects

Green city l green

Green Deal

The European Green Deal sets out how to make Europe the first climate-neutral continent by 2050. It maps a new, sustainable and inclusive growth strategy to boost the economy, improve people’s health and quality of life, care for nature, and leave no one behind.

The Green Deal spans and informs all of the Horizon Europe Pillars and Destinations. As such, there is no dedicated funding programme, apart from Horizon Europe itself. This strategy underpins Horizon Europe funding from 2021-2027. You can read more about the Pillars and funding opportunities here.

Recent Projects

Laptop l green

Open Data

The success of Europe’s digital transformation will depend on establishing effective rules to ensure trustworthy technologies, to give businesses the confidence and means to digitise, and to ensure highest privacy standards for citizens. The Data Strategy and the White Paper on Artificial Intelligence are the first pillars of the new digital strategy of the Commission. They all focus on the need to put people first in developing technology, as well as on the need to defend and promote European values and rights in how we design, make and deploy technology in the economy.

The European strategy for data aims at creating a single market for data that will ensure Europe’s global competitiveness and data sovereignty. Common European data spaces will ensure that more data becomes available for use in the economy and society, while keeping companies and individuals who generate the data in control.

Cluster 4 in Horizon Europe is dedicated to Digital, Industry and Space. The overarching vision behind the proposed investments under Cluster 4 is that of Europe shaping competitive and trusted technologies for a European industry with global leadership in key areas, enabling production and consumption to respect the boundaries of our planet, and maximising the benefits for all parts of society in the variety of social, economic and territorial contexts in Europe.

This will build a competitive, digital, low-carbon and circular industry, ensure sustainable supply of raw materials, develop advanced materials and provide the basis for advances and innovation in  global challenges to society.

Recent Projects

Electric car l green

Mobility

The European Green Deal calls for a 90% reduction in greenhouse gas emissions from transport in order for the EU to become a climate-neutral economy by 2050, while also working towards a zero-pollution ambition. To achieve this systemic change, we need to (1) make all transport modes more sustainable, (2) make sustainable alternatives widely available in a multimodal transport system and (3) put in place the right incentives to drive the transition.

Climate, Energy and Mobility is the focus for Cluster 5 in Horizon Europe. This clusters aims to fight climate change by better understanding its causes, evolution, risks, impacts and opportunities, and by making the energy and transport sectors more climate and environment-friendly, more efficient and competitive, smarter, safer and more resilient

More information here.

Recent Projects

Leaf l green

Agriculture

The Farm to Fork Strategy is at the heart of the Green Deal. It addresses comprehensively the challenges of sustainable food systems and recognises the inextricable links between healthy people, healthy societies and a healthy planet. The strategy is also central to the Commission’s agenda to achieve the United Nations’ Sustainable Development Goals (SDGs). All citizens and operators across value chains, in the EU and elsewhere, should benefit from a just transition, especially in the aftermath of the COVID-19 pandemic and the economic downturn. A shift to a sustainable food system can bring environmental, health and social benefits, offer economic gains and ensure that the recovery from the crisis puts us onto a sustainable path. Ensuring a sustainable livelihood for primary producers, who still lag behind in terms of income, is essential for the success of the recovery and the transition.

Cluster 6 under Horizon Europe ringfences innovation grant funding for Food, Bioeconomy, Natural Resouces, Agriculture & Environment. This cluster aims at reducing environmental degradation, halting and reversing the decline of biodiversity on land, inland waters and sea and better managing natural resources through transformative changes of the economy and society in both urban and rural areas. It will ensure food and nutrition security for all within planetary boundaries through knowledge, innovation and digitalisation in agriculture, fisheries, aquaculture and food systems and steer and accelerate the transition to a low carbon, resource efficient circular economy and sustainable bioeconomy, including forestry.

More information here.